Track laying begins on Nagpur Metro Phase 2 Reach-4A from Prajapati Nagar to Transport Nagar; 78% work done
Images are not validated/verified
Work on the 5.33-km elevated Reach-4A corridor of the Aqua Line extension is 78 per cent complete, with track laying started on a one-km stretch.
Good news has come from Metro Phase 2 for people in East Nagpur. Work on the 5.33-km elevated Reach-4A corridor being built from Prajapati Nagar to Transport Nagar is moving towards its final stage. According to senior officials, 78 per cent of the work on this extension of the Aqua Line has been completed so far.
Foundation work for the viaduct on this route is fully complete. Track laying has also begun on a one-km stretch.
The elevated corridor will pass through Central Avenue and Bhandara Road. Three major stations are being built on it: Pardi, Kapsi Khurd and Transport Nagar. When the route opens, it will bring major relief to thousands of daily commuters travelling to Pardi, Kalamna Market, nearby industrial areas and Symbiosis University.
On the current status of work, all 596 piles and 127 pile caps are complete. Of a total of 199 piers, 190 are ready. Of 197 pier caps, 167 have been installed.
Of 1,844 proposed segments, 1,535 have been cast. Of 181 viaduct spans, 136 have been erected.
The biggest feature of the corridor is a 2-km double-decker viaduct being built over the existing Pardi flyover. On this stretch, the launching girder "Shikhar" has completed 1.25 km of its 1.95-km target. It is described as the city's third double-decker bridge.
Three large launching girders, "Shivalik", "Shikhar" and "Giri", are deployed to place the segmental box girders. "Giri" completed its share of the work in October itself. "Shivalik" is expected to complete its assigned target by January 2027 and "Shikhar" by July 2027.
The contract for this elevated corridor was awarded to Kalpataru Projects International Limited in November 2024. Work then began under an agreement between Maha Metro and the National Highways Authority of India. With a one-km stretch now handed over for track laying, hopes of an early opening of the route have risen further.
Reach readers on the ward they actually live in.
Advertise with Prime Time 24Reach readers on the ward they actually live in.
Advertise with Prime Time 24Reach readers on the ward they actually live in.
Advertise with Prime Time 24Choose primetime24.com as a preferred source on Google Google shows more stories from your preferred sources in Top Stories.
Reach readers on the ward they actually live in.
Advertise with Prime Time 24
Comments
No comments yet. Be the first.