Nagpur Metro Pardi route 78% complete, track laying begins on about 1 km

Workers lay track on an elevated metro viaduct above busy city roads in daylight Images are not validated/verified
Civic PT24 team

Work on the 5.33-km Reach-4A stretch between Prajapati Nagar and Transport Nagar is advancing fast, with viaduct foundation work fully done.

Work on the Reach-4A route of Nagpur Metro's second phase, being built between Prajapati Nagar and Transport Nagar, is moving ahead rapidly. The extended stretch is 5.33 km long. Foundation work for the viaduct has been completed in full, and track laying has begun on about one kilometre of the route.

Senior officials said 78 per cent of the work on the entire project has been completed so far.

Three stations are coming up on the route: Pardi, Kapsi Khurd and Transport Nagar. The elevated metro corridor will connect Central Avenue and Bhandara Road. Once it opens, travel in East Nagpur will become considerably easier. Thousands of people who commute daily to Pardi, Kalamna market, the surrounding industrial areas and Symbiosis University will find their journeys faster and more convenient.

All 596 piles and 127 pile caps required for the viaduct have been completed. Of the 199 columns, 190 are ready. Of 197 pier caps, 167 have been installed. Of the 1,844 segments fixed for the route, 1,535 have been cast. Of the 181 viaduct spans in all, 136 have been placed on site.

Three launching girders, Shivalik, Shikhar and Giri, have been assigned to install the box girders on the route. Giri finished its work in October itself. Of the other two, Shivalik is expected to meet its target by January 2027 and Shikhar by July 2027.

The highlight of the engineering of the whole project is the two-km double-decker viaduct being built over the existing Pardi flyover. On this section, the Shikhar launching girder has so far completed 1.25 km of the 1.95 km assigned.

The contract to build the route was awarded to Kalpataru Projects International Limited in November 2024. Actual work began after an agreement between Maha Metro and the National Highways Authority of India. With one kilometre now handed over for track laying, the project has reached an important milestone. If the remaining work proceeds at the same pace, the way will open for metro service to begin soon in East Nagpur.