Maha-Metro invites tenders for electrical system of Thane Integral Ring Metro

Daylight city road with surveyors, vehicles and an elevated metro viaduct Images are not validated/verified
Civic PT24 team

Maha-Metro has begun the tender process for planning the electrical system of the 29-km Thane Integral Ring Metro, with key stages targeted for completion in six months.

The Thane Integral Ring Metro project has been taken up to ease growing traffic congestion in Thane city and give commuters better facilities. Work on it is now picking up pace. Maharashtra Metro Rail Corporation Limited (Maha-Metro) has started the tender process for planning the project's electrical system, which is considered highly important. The step brings the dream of a metro in Thane a step closer to reality.

Under the proposed plan, detailed drawings of the metro's electrical system will be prepared, the route will be surveyed on site and a thorough technical feasibility study will be carried out. Maha-Metro has set a target of completing all these key stages in the next six months. The tender will make it possible to plan properly for uninterrupted power supply on the elevated and underground sections, overhead wires, the exact positions of electric poles and the power distribution system.

The Thane Integral Ring Metro proposed by Maha-Metro is 29 km long. It will run from New Thane to Thane Junction, with 26 km elevated and 3 km underground.

A total of 22 stations are proposed along the route, of which 20 are elevated and two are underground. A modern car depot will also be built at Kasarvadavali for the maintenance and repair of metro trains.

On the technical side, a 25 kV AC flexible overhead equipment (OHE) system is proposed for the elevated section. A 25 kV AC ROCS overhead system will be used for the underground section. A consultant agency will carry out a comprehensive study to coordinate the two systems. For power distribution, two receiving substations, RSS-1 at the Kasarvadavali depot and RSS-2 at Shivaji Chowk, will be built.

As per the Railway Board's Schedule of Dimensions, the height of the contact wires has been fixed at 5,000 mm on the elevated section, 4,318 mm on the underground section and 5,200 mm in the open area of the depot. The system will be put up in coordination with various authorities.