Pimpri Chinchwad expects extra 167 MLD from Bhama Askhed dam from March 2027

Workers lower large pipes into a trench at a construction site in daylight Images are not validated/verified
Civic PT24 team

The civic body aims to finish work on the Bhama Askhed scheme by the end of January, test the water in February and start supply in March.

Residents of Pimpri Chinchwad have endured water supply on alternate days for the past seven years. A 10 per cent water cut has also been in force on top of that since October 16. They may get some relief in the new year, as the city is due to receive an additional 167 million litres a day (MLD) from the Bhama Askhed dam in March 2027.

The municipal administration has prepared to complete work on the scheme by the end of January. The water will then be tested in February, and actual supply will begin from March.

The city's population is growing rapidly, and demand for water is rising with it. The municipal administration is finding it difficult to balance available water against growing demand. Supply is low and irregular in many parts of the city, causing hardship to residents. Alternate-day supply, with a 10 per cent cut on top, has added to their difficulties.

For this reason, residents are looking to the additional water from the Bhama Askhed dam in Khed taluka. Under the scheme, 167 MLD will be brought through a closed pipeline to the water treatment centre at Chikhli. Once this water arrives, the city's total supply will rise and the pressure on the present system will ease.

After the 10 per cent cut, the city is currently getting 520 MLD from the Pavana dam, 90 MLD from the Andra dam and 25 MLD from the MIDC. This totals 635 MLD. Adding the 167 MLD from Bhama Askhed would give the city's water supply major support.

Work on the scheme had stalled, so a new contractor has been appointed. The pace of work has since picked up and it is being reviewed continuously. Ajay Suryawanshi, joint city engineer of the municipal corporation, said the work would be completed by the end of January 2027 and the water tested in February. According to him, the city will actually receive the increased 167 MLD in March.