Before buying a flat, check possession date and builder extensions on MahaRERA

Two people review papers at a construction site, with workers and cranes behind them Images are not validated/verified
Business PT24 team

MahaRERA records show a project's registered completion date, updates and extension orders, but the date there is not automatically the possession date in your agreement for sale.

A flat buyer's first question is often when possession will be given. The salesperson says next year, or within 12 months, or by March, or very soon. But the buyer need not depend on such statements. The Maharashtra Real Estate Regulatory Authority (MahaRERA) holds a record for every registered project. It shows the registered completion date, project updates, building-wise completion details and, where applicable, information and orders related to extensions. MahaRERA asks promoters to keep project information updated.

One important difference must be remembered. The date on a project's MahaRERA record is not automatically the possession date in the agreement for sale for your flat. If a project is delayed, this difference matters a great deal.

First, get the project's correct MahaRERA registration number. It generally looks like P521000XXXXXX. Do not search only by the builder's brand name, because large developers can have several projects with similar names, several phases, separate legal entities and separate registrations. In a large township, the registration number and completion date of one phase can differ from another. Check the number for the same phase and the same building in which you are buying.

Look at the proposed completion date in the record, but do not stop at the first date. A project registered with a 2024 date may later show a new date because of an extension that was granted. Suppose the original date was 31 December 2025 and the record now says 31 December 2027. That is not a small difference. The buyer should then ask why the date changed and through what regulatory action. According to MahaRERA, the building-wise completion date cannot go beyond the revised proposed date.

Under MahaRERA's current guidance, a project's registration can generally be extended by up to one year in special circumstances under Section 6. A further extension can be considered under Section 7(3), which covers situations such as the consent of allottees or an application made with reasons and documents. An extension does not mean the project is complete. It means only that the regulatory timeline has been extended through the prescribed process. So look at the actual progress of construction: the percentage of work done, building-wise progress, uploaded updates, approvals, the occupancy certificate where applicable, and photographs or other documents. Also check whether the building or wing with your flat is really complete. Under a single registration, one tower may be complete while another is still being built.

MahaRERA also requires quarterly and annual updates. These show the promoter's reporting over time, not just a snapshot of one day. For example, a project may have been registered in 2023, its date changed in 2025, an extension granted in 2026 and the work may still be incomplete. That story is very different from the builder's claim that possession will be given soon.

Next, read your agreement for sale. It states the possession date agreed between the promoter and the allottee. In MahaRERA's appellate decisions, the date in the agreement has been treated as important when considering rights over delay under Section 18 of RERA. So remember two dates: the project's MahaRERA timeline and the possession date written in the agreement. If the two differ widely, ask the builder the reason before signing.

Section 18 deals with the situation in which the promoter fails to give possession in accordance with the agreement or by the stipulated date. According to MahaRERA's decisions, depending on the circumstances and the allottee's choice, there may be rights related to a refund or interest for the period of delay. Which route to choose depends on the facts, the agreement and the applicable law. But the first step is straightforward: know the date.

If the completion date has already passed, do not panic, but do not ignore it either. MahaRERA maintains lists of projects affected by lapsed dates. According to it, the bank accounts of some projects stopped because of a lapsed date can be frozen, and promoters cannot execute an agreement for sale or a sale deed until the prescribed conditions are met. A lapsed date is a signal for scrutiny, not an automatic verdict on the developer's intent or quality.

Write down five dates: MahaRERA's original completion date, the revised date, the extension date, the possession date in the agreement, and the date on which legally valid possession is actually given. If the salesperson gives any other date, ask for it in writing, along with the current MahaRERA registration number and project details. The aim is not confrontation but building a paper record. Keep the registration page, extension order, project updates, building details, occupancy certificate, agreement, payment records and copies or screenshots of important conversations with the promoter in one folder.

MahaRERA is a good source, but not a substitute for other checks. Title and legal documents, sanctioned plans, approvals, the status of construction, society or maintenance arrangements, access road and amenities should also be examined. MahaRERA registration is not a guarantee that a project will be completed on time. Its value is that it gives a regulatory record that can be checked.