Andheri West-Khar West Metro 2B stretch in final phase, MMRDA targets March 2027 opening
Images are not validated/verified
Only three girders remain on the Andheri West-Sarswat Nagar section, but a building that must be demolished for a crane may push completion to June-July 2027.
Relief may be on the way for lakhs of Mumbaikars troubled by heavy daily traffic, with work on the Metro line between Andheri and Khar moving a big step forward. The Mumbai Metropolitan Region Development Authority (MMRDA) has set a target of 2027 to complete this key section of the Metro 2B corridor.
Metro 2B will run from Andheri West to Mandale in Mankhurd. Work on the Andheri West-Sarswat Nagar section (Phase 2) has picked up considerable pace and has now reached its final stage. MMRDA is working on the corridor on a war footing. Only three girders remain to be erected, and the remaining work is expected to be completed in the next 8 to 10 days.
After civil construction of Phase 2 from Andheri West to Sarswat Nagar is completed, work on the technical systems will be taken up. The safety certificate required for the section will be obtained after that. MMRDA is making a strong effort to complete the process and open this Metro line to Mumbaikars in March 2027.
Once the line opens, the serious problem of traffic jams in the Andheri and Khar areas is expected to ease. Commuters will be able to travel directly from Andheri to Khar. Travel from Kashigaon to Khar West will also be possible by Metro without interruption, saving commuters time and making the journey considerably more comfortable.
MMRDA has set a target of opening the 7.53-km Metro line from Andheri West to Khar West by March. The authority is extending Metro 2A, which runs from Dahisar to Andheri West, onward from Andheri West to Mandale in Mankhurd as Metro 2B.
The Metro 2 line came into service for Mumbaikars only a few months ago. This 18.6-km line has made travel from Kashigaon (Mira Road) to Andheri West much easier. In the next phase, the 10.3-km Phase 3 from Sarswat Nagar to Chembur is expected to be operational by 2028.
MMRDA is making every effort to open the line in March 2027, but the project is being delayed by some technical hurdles in the actual work. A large crane has to be set up to erect the remaining girders, and that requires considerable space.
To free up that space, a building next to the Metro line will have to be demolished, but the demolition matter is currently stuck. Because of this hurdle, work on a 185-metre stretch has stalled. While it is being said that this section will be completed by March 2027, the technical delay means the Metro line is now expected to be actually completed by June-July 2027.
Reach readers on the ward they actually live in.
Advertise with Prime Time 24Reach readers on the ward they actually live in.
Advertise with Prime Time 24Reach readers on the ward they actually live in.
Advertise with Prime Time 24Choose primetime24.com as a preferred source on Google Google shows more stories from your preferred sources in Top Stories.
Reach readers on the ward they actually live in.
Advertise with Prime Time 24
Comments
No comments yet. Be the first.